Client
A UK managed service provider with around 110 staff supporting several hundred small and mid-sized organisations
Sector
Technology
Engagement
Dependency mapping, fallback monitoring and patching, access restriction and a client communication plan - five-week programme.
What the client needed
When a researcher published a large set of claimed zero-days in a widely used remote management product and its vendor took the hosted service offline, the client's operations director asked a blunt question: if our own platform had to be switched off tomorrow, what would still work? The honest answer was very little. Patching, alerting, scripted fixes and remote sessions all ran through one console, which was also reachable from the internet and held stored administrator credentials for client devices.
How we worked
- Mapped everything that depended on the platform, from patch deployment and antivirus status to ticket creation, backup alerts and out-of-hours call-outs.
- Chose a minimal fallback for each dependency: a secondary alerting path for servers and backups, and a manual patching procedure for the highest-risk clients.
- Moved the console behind a VPN and fixed addresses, and removed stored credentials the platform did not need to hold.
- Wrote a client note and a call script so every account manager could say the same thing within the first hour of an outage.
- Agreed in advance what to check before reconnecting after an incident: new administrators, new automation policies and unexpected agent behaviour.
- Ran a half-day exercise in which the platform was treated as unavailable and the team handled a live ticket queue.
Measured results
Results confirmed with the client. Names, counts and platform details withheld in line with our standard confidentiality terms.
- The console is no longer reachable from the open internet.
- Server and backup alerts now have a second route that does not depend on the main platform.
- In the exercise, the team triaged the simulated queue and informed all clients with the platform offline, using the prepared note.
- The number of stored privileged credentials in the platform was reduced, and the rest were rotated.
- A written reconnection checklist now exists, owned by a named person.
"We had a plan for a client's server failing. We had no plan for the tool we use to look after all their servers failing."
Working on something similar?
If this engagement looks like the kind of problem you are facing, we would be glad to compare notes by email.
Context and constraints
The provider could not take a quiet month to rebuild its tooling, and it did not want to replace the platform. The work had to be cheap, quick and not disturb the day job. We settled on lowering exposure first (network restriction and fewer stored secrets), then fallbacks, then rehearsal.
What the news actually taught
The reporting on the N-central shutdown was a reminder of two separate risks. One is that the product might have flaws. The other is that when it is pulled, you are left without it for an unknown number of days, with no estimate given. The client had only thought about the first. Planning for the second is mostly dull: a list, an alternate alert path, a call script.
Where it was harder than expected
Out-of-hours cover turned out to depend on the platform in ways nobody had written down: on-call engineers used it to see which client was calling in about what. We replaced that with a shared sheet that is kept up to date weekly. It is not elegant, but it works with the power off.
Lessons learned
Your management tool is part of every client's attack surface and every client's service. Keep it off the open internet, keep as few secrets inside it as you can, and practise running without it. Do the exercise before you need it.
If you would like to test your own plan, email sales@halfteck.com.
Source: BleepingComputer, 9 November 2026.